Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/D, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B Monthly Environmental Monitoring &
Audit Report
- AUGUST 2016 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
12 September
2016 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3.
status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air
Quality Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7.
Cumulative Construction Impact due to the Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.1 Summary
of the current status on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.3 Summary
of submission status under FEP-02/364/2009
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.5 Summary
of submission status under FEP-01/364/2009
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.7 Summary
of submission status under FEP-05/364/2009/A
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.9 Summary
of submission status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of submission status under FEP-09/364/2009/B
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/B
Table 4.1 Noise Monitoring
Stations
Table 4.2 Real
Time Noise Monitoring Stations
Table 4.3 Air
Quality Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/18
Table 5.2 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real
Time Noise Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air
Quality Monitoring Station for Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring
Station for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring
Station for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring
Stations for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Table 5.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary of Environmental
Inspections for Contract no. HY/2009/15
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table
8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting Month
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Modification and Construction of Sign Gantries / Traffic Signs
·
Maintenance works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Stage 4 backfilling works
·
Reinstatement of outfall
·
Road and Drain works
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Remedial works against water leakage and concrete defects
·
Installation of precast concrete covers
·
Middle and side wall construction
·
Tunnel top slab construction
·
Removal of Eastern Bulkhead Wall
·
Waterproofing layer at tunnel top slab
·
Removal of ELS S4
·
Excavation work
·
ELS S1 layer installation
·
Pumping test
·
Removal of remaining sheet piles and temporary seawall blocks
·
Erection of hoarding for the demolition of ex-WSD Salt Water Pumping
Station Demolition of ex-WSD salt water pumping station
·
Backfilling works of HKE Cable connection works
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Construction of EVB
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge construction and segment erection
·
Hing Fat Street modification works
·
Hing Fat Street Slip Road Bridge E L3 railing construction
·
EVB waterproofing & back filling works
·
Pier 22 to 28 Tie Beam construction
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
·
Grouting
·
Construction of MVB and CWB Tunnel
·
Construction of concrete plug
·
Excavation and lateral support installation for CWB tunnel
Contract
no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under
FEP-10/364/2009B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Excavation and Lateral Support for U-structure,
·
Grouting works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
·
Construction of Ventilation Buildings, inclusive of Administration
Building, East Ventilation Shaft, West Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
Noise Monitoring
Air Quality Monitoring
The 24hr TSP monitoring at air quality
monitoring station CMA1b was rescheduled from 09 August 2016 to 10 August 2016.
The 24hr TSP monitoring at air quality
monitoring station CMA3a was rescheduled from 26 August 2016 to 27 August 2016.
The 24hr TSP monitoring at air quality
monitoring station CMA5b was rescheduled from 28 July 2016 and 26 August 2016
to 29 July 2016 and 27 August 2016 respectively.
The 24hr TSP monitoring at air quality
monitoring station MA1e was rescheduled from 15 August 2016 and 20 August 2016
to 16 August 2016 to 22 August 2016 respectively.
Complaints, Notifications of Summons
and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Modification and Construction of Sign Gantries / Traffic Signs
·
Maintenance works
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under
FEP-02/364/2009
·
Reinstatement of outfall
·
Road and Drain works
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Concreting of protective screeding on tunnel top slab
·
Tunnel wall and top slab construction
·
ELS S4 removal
·
Waterproofing layer at tunnel top slab
·
Tunnel backfilling
·
General cleaning of OHVD & tunnel base slap, carrier drain and cross
road duct.
·
Bulkhead wall removal works
·
Excavation work
·
Strut installation
·
Demolition of ex-WSD Salt Water Pumping Station
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge construction
·
Hing Fat Street modification works
·
Hing Fat Street Slip Road Bridge E L3 railing construction
·
EVB waterproofing & back filling works
·
Pier 22 to 28 Tie Beam construction continues
·
Oil Street drainage works
·
Excavation / Construction of retaining wall
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009/B
·
Grouting
·
Construction of MVB and CWB Tunnel
·
Construction of concrete plug
·
Excavation and lateral support installation for CWB tunnel
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Excavation and Lateral Support for U-structure,
·
Grouting works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
·
Construction of Ventilation Buildings, inclusive of Administration
Building, East Ventilation Shaft/Building, West Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/D and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D,
FEP-09/364/2009/B, FEP-10/364/2009B and FEP-11/364/2009B to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/D, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-05/364/2009/A,
FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B
during the period 27 July 2016 to 26 August 2016.
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results – summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai Bypass” and
“Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called
“the Project”) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai
Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008)
have been approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
·
Associated road lighting, road signing, traffic control and surveillance
system; and
·
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further Environmental
Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield
Depot – Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587
1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912
3010 |
|
Chun Wo – Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2634
1626 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr.
Terry Tsang |
6683
9394 |
|||
Environmental
Officer |
Ms. Wendy
Ng |
9803
0057 |
|||
Assistant
Environmental Engineer |
Ms. Connie Chan |
6157 7057 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827
9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570
8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. Tom Ding |
3757 8217 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
|
Environmental Officer |
Mr. Chris Chan |
2823
1161 |
|||
Assistant Environmental Engineer |
Mr. Christy So |
3937
1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor’s
Representative |
Mr. Rex Chan |
3557
6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Mr. Harry Wong |
3557 6348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
2566
8061 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Mr. Andrew
Wong |
3467
4277 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Mr. Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823 1111 |
21406799 |
Site
Agent |
Colman Wong |
9730 0806 |
|||
Environmental
Officer |
Malcolm
Leung |
3973 0850 |
|||
Environmental
Supervisor |
Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Modification and Construction of Sign Gantries / Traffic Signs
·
Maintenance works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Stage 4 backfilling works
·
Reinstatement of outfall
·
Road and Drain works
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Remedial works against water leakage and concrete defects
·
Installation of precast concrete covers
·
Middle and side wall construction
·
Tunnel top slab construction
·
Removal of Eastern Bulkhead Wall
·
Waterproofing layer at tunnel top slab
·
Removal of ELS S4
·
Excavation work
·
ELS S1 layer installation
·
Pumping test
·
Removal of remaining sheet piles and temporary seawall blocks
·
Erection of hoarding for the demolition of ex-WSD Salt Water Pumping
Station Demolition of ex-WSD salt water pumping station
·
Backfilling works of HKE Cable connection works
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
·
Construction of EVB
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge construction and segment erection
·
Hing Fat Street modification works
·
Hing Fat Street Slip Road Bridge E L3 railing construction
·
EVB waterproofing & back filling works
·
Pier 22 to 28 Tie Beam construction
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under
FEP-09/364/2009B
·
Grouting
·
Construction of MVB and CWB Tunnel
·
Construction of concrete plug
·
Excavation and lateral support installation for CWB tunnel
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Excavation and Lateral Support for U-structure,
·
Grouting works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009B
·
Construction of Ventilation Buildings, inclusive of Administration
Building, East Ventilation Shaft, West Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Modification and Construction of Sign Gantries / Traffic Signs
·
Maintenance works
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under
FEP-02/364/2009
·
Reinstatement of outfall
·
Road and Drain works
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Concreting of protective screeding on tunnel top slab
·
Tunnel wall and top slab construction
·
ELS S4 removal
·
Waterproofing layer at tunnel top slab
·
Tunnel backfilling
·
General cleaning of OHVD & tunnel base slap, carrier drain and cross
road duct.
·
Bulkhead wall removal works
·
Excavation work
·
Strut installation
·
Demolition of ex-WSD Salt Water Pumping Station
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge construction
·
Hing Fat Street modification works
·
Hing Fat Street Slip Road Bridge E L3 railing construction
·
EVB waterproofing & back filling works
·
Pier 22 to 28 Tie Beam construction continues
·
Oil Street drainage works
·
Excavation / Construction of retaining wall
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B
·
Grouting
·
Construction of MVB and CWB Tunnel
·
Construction of concrete plug
·
Excavation and lateral support installation for CWB tunnel
Contract no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip
Road 8) under FEP-10/364/2009
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Excavation and Lateral Support for U-structure,
·
Grouting works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
·
Construction of Ventilation Buildings, inclusive of Administration
Building, East Ventilation Shaft/Building, West Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2015 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further Environmental Permit |
24 Nov 2015 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central – Wan Chai
Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS0152-16 |
18 Feb 2016 |
25 Feb 2016 to 24 Aug 2016 |
Cancelled |
GW-RS0243-16 |
11 Mar 2016 |
14 Mar 2016 to 13 Sep 2016 |
Cancelled |
|
GW-RS0384-16 |
19 Apr 2016 |
22 Apr 2016 to 19 Oct 2016 |
Valid |
|
GW-RS0435-16 |
03 May 2016 |
08 May 2016 to 07 Nov 2016 |
Valid |
|
GW-RS0482-16 |
17 May 2016 |
19 May 2016 to 18 Nov 2016 |
Valid |
|
GW-RS0486-16 |
17 May 2016 |
19 May 2016 to 18 Nov 2016 |
Valid |
|
GW-RS0488-16 |
17 May 2016 |
19 May 2016 to 18 Nov 2016 |
Valid |
|
GW-RS0492-16 |
20 May 2016 |
23 May 2016 to 22 Nov 2016 |
Valid |
|
GW-RS0493-16 |
20 May 2016 |
23 May 2016 to 22 Nov 2016 |
Valid |
|
GW-RS0495-16 |
20 May 2016 |
19 May 2016 to 18 Nov 2016 |
Valid |
|
GW-RS0546-16 |
27 May 2016 |
30 May 2016 to 26 Nov 2016 |
Cancelled |
|
GW-RS0592-16 |
13 Jun 2016 |
15 Jun 2016 to 12 Dec 2016 |
Valid |
|
GW-RS0636-16 |
20 Jun 2016 |
21 Jun 2016 to 19 Dec 2016 |
Valid |
|
GW-RS0822-16 |
28 Jul 2016 |
7 Aug 2016 to 31 Jan 2017 |
Valid |
|
Discharge License |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Expired |
WT00024952-2016 |
06 Jul 2016 |
31 Jul 2021 |
Valid |
|
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May
2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun
2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar
2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-pilling equipment |
GW-RS0083-16 |
01 Feb 2016 |
3 Feb 2016 to 01 Aug 2016 |
Cancelled |
GW-RS0390-16 |
22 Apr 2016 |
27 Apr 2016 to 26 Oct 2016 |
Valid |
|
GW-RS0399-16 |
27 Apr 2016 |
27 Apr 2016 to 26 Oct 2016 |
Valid |
|
GW-RS0403-16 |
27 Apr 2016 |
30 Apr 2016 to 24 Sep 2016 |
Valid |
|
GW-RS0516-16 |
20 May 2016 |
23 May 2016 to 22 Nov 2016 |
Cancelled |
|
GW-RS0593-16 |
13 Jun 2016 |
15 Jun 2016 to 12 Dec 2016 |
Valid |
|
GW-RS0803-16 |
28 Jul 2016 |
30 Jul 2016 to 27 Jan 2017 |
Valid |
|
Water
Discharge License |
WT00009691-2011 |
01 Aug 2011 |
31 July 2016 |
Expired |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
|
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping
Permit (Type 1 – Open Sea Disposal) |
EP/MD/17-041 |
23 Jun 2017 |
01 Jul 2016 to 31 Dec 2016 |
Valid |
Table
3.5 Summary of submission status
under FEP-01/364/2009
EP Condition |
Submission |
Date
of
Submission |
Condition 2.7
and 2.8 |
Works
Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental
Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement
Date of Works |
21 Jun 2011 |
Condition
2.11 |
Landscape Plan (Revision B) |
20 Nov
2012 |
Condition 2.9 |
Noise Management Plan (Revision B) |
13 Jan
2012 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
3.1.8.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15
Nov 2010 |
Permit
issued |
Valid |
Notification
of Works Under APCO |
322293 |
07
Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0335-16 |
07 Apr 2016 |
08 Apr 2016 to 30 Sep 2016 |
Cancelled |
GW-RS0438-16 |
03 May 2016 |
05 May 2016 to 30 Sep 2016 |
Cancelled |
|
GW-RS0459-16 |
09 May 2016 |
11 May 2016 to 31 Aug 2016 |
Valid |
|
GW-RS0564-16 |
06 Jun 2016 |
08 Jun 2016 to 31 Oct 2016 |
Cancelled |
|
GW-RS0577-16 |
06 Jun 2016 |
08 Jun 2016 to 31 Oct 2016 |
Cancelled |
|
GW-RS0669-16 |
24 Jun 2016 |
01 Jul 2016 to 31 Dec 2016 |
Valid |
|
GW-RS0700-16 |
04 Jul 2016 |
06 Jul 2016 to 31 Oct 2016 |
Valid |
|
GW-RS0705-16 |
04 Jul 2016 |
06 Jul 2016 to 31 Oct 2016 |
Valid |
|
GW-RS0762-16 |
14 Jul 2016 |
16 Jul 2016 to 31 Oct 2016 |
Valid |
|
GW-RS0847-16 |
15 Aug 2016 |
17 Aug 2016 to |
Valid |
|
GW-RS0874-16 |
23 Aug 2016 |
25 Aug 2016 to 30 Nov 2016 |
Valid |
|
Discharge
Licenses |
WT00013967-2012 |
17
Sep 2012 |
30
Sep 2017 |
Cancelled |
WT00014966-2013 |
08 Jan 2013 |
31 Jan 2018 |
Cancelled |
|
WT00020725-2015 |
14
Jan 2015 |
30
Jul 2017 |
Valid |
|
WT00024255-2016 |
18
May 2016 |
31
Jan 2021 |
Valid |
|
Registration
as a Chemical Waste Producer |
WPN: 8335-121-L1048-04 |
17
Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste Disposal Ordinance
(Land) |
Account No.: 7011587 |
11
Oct 2010 |
Account approved |
Valid |
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
EP Condition |
Submission |
Date
of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 6) |
19 May 2014 |
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.9.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0232-16 |
08 Mar 2016 |
9 Mar 2016 to 08 Sep 2016 |
Valid |
GW-RS0233-16 |
14 Mar 2016 |
14 Mar 2016 to 10 Sep 2016 |
Valid |
|
GW-RS0235-16 |
10 Mar 2016 |
12 Mar 2016 to 08 Sep 2016 |
Valid |
|
GW-RS0553-16 |
30 May 2016 |
30 May 2016 to 24 Nov 2016 |
Valid |
|
Registration as a Chemical Waste
Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance (Disposal by Vessel) |
7011761 |
13 Jul 2016 |
17 Jul 2016 to 31 Dec 2017 |
Valid |
Water Discharge Licence
(Discharge at TPCWAW) |
WT00020601-2014 |
18 Mar 2015 |
18 Mar 2015 to 31 Mar 2017 |
Valid |
Water Discharge Licence
(Discharge at TPCWAE) |
WT00024951-2016 |
8 Jul 2016 |
8 Jul 2016 to 31 Dec 2017 |
Valid |
Water Discharge Licence(
Discharge at TS1) |
WT00024874-2016 |
20 Jul 2016 |
20 Jul 2016 to 31 Mar 2021 |
Valid |
Table 3.9 Summary of submission status under
FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 Mar
2011 |
Amendment for Management
Organization of Main Construction Companies |
16 May
2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar
2011 |
Condition 2.8 |
Location Plan |
15 Mar
2011 |
Condition 2.9 |
Noise Management Plan |
6 May
2011 |
Condition
2.10 |
Landscape
Plan (Rev.3) |
30 Jan 2015 |
Contract no. HY/2009/19 – Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
3.1.10.
The current status on licences and/or permits
on environmental protection pertinent and submission
under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table
3.11.
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Superseded |
|
24 Nov 2015 |
N/A |
Valid |
||
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10
Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24
Mar 2011 |
N/A |
Valid |
Application
for Vessel Disposal |
7012306 |
21
July 2011 |
N/A |
Valid |
Construction
Noise Permits (CNP) for non-piling equipment |
GW-RS0197-16 |
02 Mar 2016 |
02 Mar 2016 to 01 Sep 2016 |
Cancelled |
GW-RS0330-16 |
05 Apr
2016 |
05 Apr
2016 to
04 Oct 2016 |
Cancelled |
|
GW-RS0506-16 |
20 May 2016 |
23 May 2016 to 18 Nov 2016 |
Valid |
|
GW-RS0551-16 |
01 Jun
2016 |
18 Jun
2016 to 17
Dec 2016 |
Valid |
|
GW-RS0614-16 |
16 Jun 2016 |
16 Jun 2016 to 15 Dec 2016 |
Cancelled |
|
GW-RS0851-16 |
09 Aug 2016 |
09 Aug 2016 to 08 Feb 2017 |
Valid |
|
Water
Discharge License |
WT00010093-2011 |
17 Aug 2012 |
30 Sep 2016 |
Valid |
WT00010865-2011 |
03 Nov 2011 |
30 Nov 2016 |
Cancelled |
Table 3.11 Summary of submission status under
FEP-07/364/2009/D
EP Condition |
Submission |
Date of Submission |
Condition 2.13 |
Landscape Plan (Rev.4) |
22 March 2016 |
Condition 2.9 |
Noise Management Plan (Rev.4) |
15
February 2016 |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West
3.1.11.
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-09/364/2009/B for contract no.
HK/2012/08 showed in Table 3.12 and Table 3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
N/A |
Valid |
FEP-06/356/2009 |
5 March 2013 |
N/A |
Valid |
|
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
5213-134-C3790-01 |
8 Mar 2013 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0079-16 |
1 Feb 2016 |
03 Feb 2016 to 02 Aug 2016 |
Expired |
GW-RS0212-16 |
8 Mar 2016 |
10 Mar 2016 to 08 Sep 2016 |
Cancelled |
|
GW-RS0386-16 |
20 Apr 2016 |
22 Apr 2016 to 19 Oct 2016 |
Cancelled |
|
GW-RS0583-16 |
10 Jun 2016 |
11 Jun 2016 to 09 Dec 2016 |
Valid |
|
GW-RS00739-16 |
12 Jul 2016 |
14 Jul 2016 to 12 Jan 2017 |
Valid |
|
GW-RS0902-16 |
24 Aug 2016 |
26 Aug 2016 to 25 Feb 2017 |
Valid |
|
GW-RS0749-16 |
12 Jul 2016 |
14 Jul 2016 to 12 Jan 2017 |
Cancelled |
|
Water Discharge Licence |
WT00018223-2014 |
28 Jan 2014 |
31 Jan 2019 |
Cancelled |
WT00020594-2014 |
22 Dec 2014 |
31 Jan 2019 |
Valid |
Table
3.13 Summary
of submission status under FEP-09/364/2009/B
Submission |
Date of Submission |
|
Condition 2.9 |
Noise Management Plan (Rev.2) |
9 July 2013 |
Condition 2.14 |
Landscape Plan (Rev.4) |
24 August 2015 |
Contract
no. HY/2010/08 –Central – Wanchai Bypass Tunnel – Tunnel (Slip Road 8)
3.1.12.
The current status on licences and/or permits on environmental protection
pertinent and submission under FEP-10/364/2009/B for contract no. HK/2012/08
showed in Table 3.14 and Table 3.15.
Table
3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2010/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-10/364/2009/B |
26
Jul 2013 |
NA |
Valid |
FEP-07/356/2009 |
26
Jul 2013 |
NA |
Valid |
|
Notification of Works Under APCO |
357176 |
2013-04-02 |
NIL |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
2013-03-27 |
NIL |
Valid |
Billing Account under Waste Disposal
Ordinance |
7017170 |
2013-03-27 |
NIL |
Valid |
Water Discharge
License |
WT0001651-2013 |
2013-07-09 |
2018-07-28 |
Cancelled |
WT00020468-2014 |
2014-12-03 |
2018-07-31 |
Valid |
|
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RW0061-16 |
02 Feb 2016 |
02 Feb 2016 to 31 Jul 2016 |
Cancelled |
GW-RS0264-16 |
18 Mar 2016 |
18 Mar 2016 to 17 Sep 2016 |
Valid |
|
GW-RS0357-16 |
22 Apr 2016 |
22 Apr 2016 to 21 Oct 2016 |
Valid |
|
GW-RS0362-16 |
22 Apr 2016 |
22 Apr 2016 to 21 Oct 2016 |
Cancelled |
|
GW-RS0407-16 |
20 Apr 2016 |
20 Apr 2016 to 19 Oct 2016 |
Valid |
|
GW-RS0434-16 |
05 May 2016 |
24 May 2016 to 23 Nov 2016 |
Valid |
|
GW-RS0442-16 |
06 May 2016 |
16 May 2016 to 15 Nov 2016 |
Valid |
|
GW-RS0531-16 |
06 Jun 2016 |
06 Jun 2016 to 05 Dec 2016 |
Valid |
|
GW-RW0240-16 |
04 May 2016 |
04 May 2016 to 28 Oct 2016 |
Valid |
|
GW-RS0533-16 |
26 May 2016 |
26 May 2016 to 23 Nov 2016 |
Valid |
|
GW-RS0779-16 |
14 Jul 2016 |
14 Jul 2016 to 13 Jan 2017 |
Valid |
|
GW-RS0838-16 |
03 Aug 2016 |
03 Aug 2016 to 31 Aug 2016 |
Cancelled |
|
GW-RS0869-16 |
20 Aug 2016 |
20 Aug 2016 to 30 Dec 2016 |
Valid |
|
GW-RS0888-16 |
23 Aug 2016 |
02 Sep 20156 to 28 Feb 2017 |
Valid |
Table
3.15 Summary
of submission status under FEP-10/364/2009/B
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.3) |
03 January 2014 |
Condition 2.14 |
Landscape Plan (Rev.2) |
19 May 2014 |
Condition 2.16 |
Additional Mitigation Plan (Rev.2) |
18 February 2015 |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/B
3.1.13.
The current status on licenses and/or permits on environmental
protection pertinent and submission under FEP-11/364/2009/B for contract no.
HY/2011/08 showed in Table 3.16 and Table 3.17.
Table
3.16 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2011/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
N/A |
Valid |
Notification of Works Under APCO |
LCAC-EN-LE-00017 |
7 Mar 2014 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-121-L2837-01 |
19 Apr 2016 |
N/A |
Valid |
5213-151-L2837-02 |
09 Oct 2015 |
N/A |
Registered |
|
5213-134-L2898-01 |
16 Nov 2015 |
N/A |
Registered |
|
Billing Account under Waste Disposal
Ordinance |
7019640 |
27 Mar
2014 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0147-16 |
17 Feb 2016 |
19 Feb 2016 to 31 Jul 2016 |
Expired |
GW-RS0159-16 |
17 Feb 2016 |
18 Feb 2016 to 31 Jul 2016 |
Expired |
|
GW-RS0222-16 |
8 Mar 2016 |
9 Mar 2016 to 31 Aug 2016 |
Valid |
|
GW-RS0284-16 |
23 Mar 2016 |
24 Mar 2016 to 31 Aug 2016 |
Valid |
|
GW-RS0419-16 |
29 Apr 2016 |
1 May 2016 to 31 Oct 2016 |
Valid |
|
GW-RS0520-16 |
24 May 2016 |
01 Jun 2016 to 30 Nov 2016 |
Valid |
|
GW-RS0538-16 |
24 May 2016 |
01 Jun 2016 to 30 Nov 2016 |
Valid |
|
GW-RS0626-16 |
22 Jun 2016 |
1 Jul 2016 to 31 Dec 2016 |
Valid |
|
GW-RS0645-16 |
22 Jun 2016 |
1 Jul 2016 to 31 Dec 2016 |
Valid |
|
GW-RS0801-16 |
29 Jul 2016 |
1 Aug 2016 to |
Valid |
|
GW-RS0811-16 |
28 Jul 2016 |
1 Aug 2016 to |
Valid |
|
GW-RS0891-16 |
25 Aug 2016 |
1 Sep 2016 to |
Valid |
|
GW-RS0892-16 |
25 Aug 2016 |
1 Sep 2016 to |
Valid |
|
Water Discharge Licence |
WT00020242-2014 |
04
Nov 2014 |
30
Nov 2019 |
Valid |
WT00020246-2015 |
15
Jul 2015 |
31
Jul 2019 |
Valid |
|
WT00022753-2015 |
3
May 2016 |
30
Apr 2021 |
Valid |
|
WT00024561-2016 |
30
May 2016 |
31
May 2021 |
Valid |
Table 3.17 Summary
of submission status under FEP-11/364/2009/B
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.2) |
27 Jan 2015 |
Condition 2.14 |
Landscape Plan (Rev.2) |
18 Feb 2015 |
Condition 2.13 |
Operational Air Quality Management Plan for West Ventilation Building
(Rev.0) |
25 Nov 2014 |
Condition 2.13 |
Operational Air Quality Management Plan for East Ventilation Building
and East Vent Shaft (Rev.0) |
18 Feb 2015 |
Noise
Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon-day
Gun Area |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist
Church Henrietta Secondary School |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
*M8 |
City Hall |
* Remark 1: Location ID has been updated from M7 to
M8 for City Hall
* Remark 2: M7e has become a reference station
starting from 7 Aug 2012
Real time Noise Monitoring
Stations
4.1.2.
The noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.2 Real Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitfield Depot |
North
Point |
RTN2a |
Hong Kong Electric
Centre |
North Point |
RTN3 |
Po Leung Kuk Yu Lee
Mo Fan Memorial School |
Tin Hau |
RTN4 |
Causeway Bay
Community Centre |
Noise
Monitoring Parameters, Frequency and Duration
4.1.3.
The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
· One set of measurements between 0700
and 1900 hours on normal weekdays.
4.1.5.
Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 - hours basis when noise
generating activities are underway:
· One set of measurements between 0700
and 1900 hours on normal weekdays.
· One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
· One set of measurements between 2300
and 0700 hours on next day on everyday.
4.1.6.
If construction works are extended to include
works during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring
Equipment
4.1.7.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise measurement
agree to within 1.0 dB.
4.1.8.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.9.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements will be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality
Monitoring Stations
4.2.1.
The air quality monitoring stations for the
Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Quality Monitoring
Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil
Street Site Office** |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
Causeway
Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: As
per the ENPC meeting in March 2011, the monitoring stations CMA3a – Future CWB
site office at Wanchai Waterfront Promenade was renamed as remark.
Remarks**: The
location ID of monitoring station CMA1b was updated as “Oil Street Site Office”
in April 2013.
Remarks***: The
station ID and monitoring location was updated in December 2014 with respect to
monitoring station relocation.
Air QUALITY Monitoring
Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six days should be
undertaken when the highest dust impact occurs.
Sampling
Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
· 0.6 – 1.7 m3 per minute
adjustable flow range;
· Equipped with a timing / control device
with +/- 5 minutes accuracy for 24 hours operation;
· Installed with elapsed-time meter with
+/- 2 minutes accuracy for 24 hours operation;
· Capable of providing a minimum exposed
area of 406 cm2;
· Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
· Equipped with a shelter to protect the
filter and sampler;
· Incorporated with an electronic mass
flow rate controller or other equivalent devices;
· Equipped with a flow recorder for
continuous monitoring;
· Provided with a peaked roof inlet;
· Incorporated with a manometer;
· Able to hold and seal the filter paper
to the sampler housing at horizontal position;
· Easily changeable filter; and
· Capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory
Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning instruments
to handle the dust samples collected, shall be available for sample analysis,
and equipment calibration and maintenance. The laboratory should be HOKLAS
accredited.
4.2.8.
Filter paper of size 8” x 10” shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24 hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.2.11.
Current calibration certificates of
equipments are presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designated project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure 2.1
and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section)
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Contract no.
HY/2010/08 – Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
Contract no. HK/2009/01
– Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre
Contract no.
HK/2009/02 - Wan Chai Development Phase II – Central - Wan Chai Bypass at Wan
Chai East
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai West
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB)– Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix 5.1.
5.1.1
Monitoring for report of review baseline
noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20
June 2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for
the noise calculation starting from January 2012.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.1.2 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for
Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
* Remark:
M7e has become a reference station starting from 7 Aug 2012
5.1.3
No action or limit level exceedance was
recorded in this reporting month.
5.1.4
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009 and Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.5
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
noise monitoring stations are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract
no HK/2009/01
and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.6
No action or limit level exceedance was
recorded in this reporting month.
5.1.7
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.1.8 The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed divisions of
noise monitoring stations are summarized in Table 5.3 below.
Table 5.3
Noise Monitoring Stations
for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.9
No action or limit level exceedance was
recorded in this reporting month.
5.1.10
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/D
5.1.11 Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in Table 5.4
below.
Table 5.4 Noise
Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.1.12
No action or limit level exceedance was
recorded in this reporting month.
5.1.13
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2. Details
of the Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
5.1.14 The
commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02
September 2013. The proposed divisions of noise monitoring stations are
summarized in Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
5.1.15
No action or limit level exceedance was
recorded in this reporting month.
5.1.16
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.1.17 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2011/08 are summarized in Table 5.6 below:
Table 5.6
Noise Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
* Remark: M7e has become a reference station
starting from 7 Aug 2012
5.1.18
No action or limit level exceedance was
recorded in this reporting month.
5.1.19
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
5.2.1.
Real time noise monitoring at RTN4-Causeway Bay Community Centre was
commenced on 13 Jan 2013. The baseline noise level of RTN4- Causeway Bay
Community Centre has adopted the results from the baseline noise monitoring
report for EP/364/2009 in 22 April 2010 in which approved by EPD.
5.2.2.
Po Leung Kuk Yu Lee Mo Fan Memorial School granted permission for set up
on 4 Sep 2012 and real time noise monitoring station RTN3 set up was performed
on 14 Sep 2012. Real time noise baseline capturing was conducted during time
period without construction work from 21 Sep 2012 to 04 Oct 2012. Real time noise monitoring at RTN3 – Po Leung Kuk Yu Lee Mo Fan Memorial School was
commenced since 06 Oct 2012.
5.2.3.
Real-time noise monitoring station RTN2 previously located at oil Street
Community Liaison Centre was relocated to Hong Kong Electric Centre on 5 Oct
2012, which is a representative of the noise sensitive receiver City Garden.
The baseline noise level of RTN2a will adopt the results derived from the
baseline noise monitoring conducted at Hong Kong Electric Centre from 4
December 2009 to 17 December 2009.
5.2.4.
Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely
adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with
respect to the commencement of advance works for IEC parapet demolition.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.2.5.
The proposed division of noise monitoring
stations are summarized in Table 5.7 below. Real time noise
monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table 5.7 Real
Time Noise
Monitoring Stations for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Hong Kong Electric Centre |
RTN3 |
North
Point |
Po Leung Kuk Yu Lee Mo Fan Memorial School |
RTN4 |
Tin
Hau |
Causeway Bay Community Centre |
* Real time noise monitoring results and graphical presentation during restrict
hours and night time period are for information only and noise during CNP
period shall be controlled under NCO.
5.2.6.
Limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded on 09 August 2016 during daytime in the reporting month. After
checking with Contractor of HY/2009/19, no construction activities was
conducted during the recorded period while adverse weather with frequent
thunderstorm was observed and recorded across other monitoring stations at Tin
Hau and North Point District and is considered as the major noise contribution.
As such, the exceedance was considered not related to Project.
5.2.7.
Limit level exceedances were recorded at
RTN2a-Electric Centre on 09 and 10 August 2016 during daytime in the reporting
month. After checking with Contractor of HY/2009/19, no construction activity
was conducted on 09 August 2016 during the recorded period and unloading of
soil at temporary jetty was conducted on 10 August 2016 during the recorded
period. Adverse weather with frequent thunderstorm were recorded at the
monitoring period on 09 and 10 August 2016 across monitoring stations at North
Point District and is considered as the major noise contribution. As such, the
exceedance was considered as non-Project related.
5.2.8.
Limit level exceedance was recorded at
RTN3-Yue Lee Mo Fan Memorial School on 09, 10 and 17 August 2016 during daytime
in the reporting month. After checking, no construction works was conducted by
Contract HY/2009/19 on 09, 10 and 17 August 2016 around the concerned location
during the monitoring period while adverse weather with frequent thunderstorm
was recorded at the monitoring period on 09 and 10 August 2016 across
monitoring stations at Eastern District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related. On 17 August 2016, erection of U-beam
with launching girder and crane was conducted by HY/2009/19 on 17 August 2016
and no major noise is considered. As such, the exceedance was considered as
non-Project related.
5.2.9.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre on 04, 09, 11, 12, 13 and 17 August 2016
during daytime in the reporting month. After checking with the Contractor of
HY/2009/19, excavation works and rebar fixing were conducted by Contract
HY/2009/19 on 04 August 2016 around the monitoring location during the recorded
period and no major noise is considered. In addition, construction activities
and intermittent operation of PMEs including excavator, hydraulic breaker and
sheet piling rig were observed at non-CWB Project adjacent to monitoring
station was observed in August 2016. As such, the exceedances were considered
as non-Project related.
On 09 August 2016, excavation and concreting
works was conducted under Contract HY/2009/19 around the monitoring location
during the recorded periods and no major noise is considered for the works. In
addition, construction activities and intermittent operation of PMEs including
excavator, hydraulic breaker and sheet piling machine were observed at non-CWB
Project adjacent to monitoring station over August 2016. As such, the
exceedances were considered as non-Project related.
On 11 August 2016 and 12 August 2016 morning,
hand held drilling works at IEC bridge deck (Pier 24) were conducted under
HY/2009/19 and hand held breaking works beneath IEC Bridge deck was conducted
during the recorded period. No noise mitigation measure was provided for the
drilling works at IEC bridge deck on 12 August 2016 morning and was observed as
the direct noise contribution. Hence, the exceedances on 11 and 12 August 2016
were considered as related to the Project works.
On 12 August 2016 afternoon, breaking works
beneath the IEC bridge deck and concurrent excavator mounted breaking works at
Pier 23 were observed. Despite the provision of temporary noise barrier for the
ground breaking works by excavator mounted hydraulic breaker and the hand held
breaking works was observed conducted behind physical barrier, exceedances were
recorded and direct noise contribution was observed in relation to the
concurrent operation of hand held breaker and excavator mounted hydraulic
breakers opposite to the monitoring station and considered as related to the
Project works.
The ET informed the findings to Contractor of
HY/2009/19 and advised the Contractor of HY/2009/19 to review the construction sequence
to propose and implement appropriate remedial actions. Rectification measure
including provision of acoustic noise screen for bridge deck drilling works was
provided by the Contractor of HY/2009/19 on 12 August 2016 and the Contractor
of HY/2009/19 reviewed the construction sequence and committed to isolate concurrent
bridge deck drilling or hand held breaking for construction joint underneath
IEC bridge deck or excavator mounted breaking works to avoid cumulative impact
due to concurrent operations. Further checking by the ET was conducted on 14
August 2016, drilling works with acoustic noise screen was observed on IEC
bridge deck while no concurrent breaking works and drilling works was further
observed on 14 August 2016 and no further project related exceedance was
recorded.
On 13 August 2016, only excavation works was
conducted by Contract HY/2009/19 around the monitoring location during the
recorded period and no major noise is considered. In addition, construction
activities and intermittent operation of PMEs including excavator, hydraulic
breaker and sheet piling rig were observed at non-CWB Project adjacent to
monitoring station was observed in August 2016. As such, the exceedances were
considered as non-Project related.
On 17 August 2016, drilling works for tie
beam beneath IEC was conducted by Contract HY/2009/19 immediately behind
physical barrier erected around the works location. In addition, construction
activities and intermittent operation of PMEs including excavator, hydraulic
breaker and sheet piling rig were observed at non-CWB Project adjacent to
monitoring station was observed in August 2016. As such, the exceedances were
considered as non-Project related.
5.2.10.
Real time noise monitoring results measured
in this reporting period are reviewed and summarized. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 5.4.
Contract no. HY/2011/08 – Central - Wan Chai
Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with
Tunnel Commissioning
5.2.11.
The proposed division of noise monitoring
stations are summarized in Table 5.8 below. Real time noise
monitoring for major construction works under contract no. HY/2011/08 was
commenced on 19 March 2015.
Table 5.8 Real
Time Noise
Monitoring Stations for Contract
no. HY/2011/08
Location
ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Hong Kong Electric Centre |
RTN4 |
Tin Hau |
Causeway
Bay Community Centre |
* Real time noise monitoring results and
graphical presentation during restrict hours and night time period are for
information only and noise during CNP period shall be controlled under NCO.
5.2.12.
Limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded on 09 August 2016 during daytime in the reporting month. After
checking with Contractor of HY/2011/08, no construction activities was
conducted during the recorded period while adverse weather with frequent
thunderstorm was observed and recorded across other monitoring stations at Tin
Hau and North Point District and is considered as the major noise contribution.
As such, the exceedance was considered not related to Project.
5.2.13.
Limit level exceedances
were recorded at RTN2a-Electric Centre on 09 and 10 August 2016 during daytime in
the reporting month. After checking with Contractor of HY/2009/19, no
construction activity was conducted on 09 August 2016 during the recorded
period and unloading of soil at temporary jetty was conducted on 10 August 2016
during the recorded period. Adverse weather with frequent thunderstorm were
recorded at the monitoring period on 09 and 10 August 2016 across monitoring
stations at North Point District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related.
5.2.14.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre on 04, 09, 11, 12, 13 and 17 August 2016
during daytime in the reporting month. After checking with the Contractor of
HY/2011/08, no construction activities was conducted around the monitoring
location during the recorded period on 04, 09, 11, 12, 13 and 17 August 2016.
In addition, construction activities and intermittent operation of PMEs
including excavator, hydraulic breaker and sheet piling rig were observed at
non-CWB Project adjacent to monitoring station was observed in August 2016. As
such, the exceedances were considered as non-Project related.
Contract no. HY/2009/18 –
Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.3.1
Air quality monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.9 below.
Table
5.9 Air Quality Monitoring Stations for Contract
no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
5.3.2
No exceedance was recorded in the reporting
month.
5.3.3
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
5.3.4
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality
monitoring stations are summarized in Table 5.10 below.
Table 5.10 Air Quality Monitoring Station for Contract
no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.5
No exceedance was recorded in the reporting
month.
5.3.6
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.3.7
The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
air quality monitoring stations are summarized in Table 5.11
below.
Table 5.11 Air Quality Monitoring Station for Contract
no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.8
No exceedance was recorded in the reporting
month.
5.3.9
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.3.10
The commencement of construction works for Contract
no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air quality
monitoring was commenced on 14 July 2011. The
proposed division of air quality monitoring stations are summarized in Table
5.12 below.
Table 5.12
Air
Quality Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.11
No exceedance was recorded in the reporting
month.
5.3.12
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.3.13
The proposed division of air quality monitoring
stations are summarized in Table 5.13 below. Air quality monitoring
for the tunnel works under contract no. HY/2009/19 was commenced on 26 April
2011.
Table 5.13 Air Quality
Monitoring
Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
5.3.14
One 1hr TSP action limit level exceedance was
recorded on 27 August 2016 in the reporting month.
5.3.15
No construction activities was undertaken by
Contractor of HY/2009/19 around the Oil Street Site Office during the
monitoring period and no particular observation regarding air quality impact
was observed during sampling. Mitigation measures including watering for haul
road was generally implemented by the Contractor. In view of the above, the
action level exceedance was considered to be non-project related.
5.3.16
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2012/08- Wan Chai Development Phase
II – Central-Wan Chai Bypass at Wan Chai West
5.3.17
The commencement of construction works for
Contract no. HK/2012/08 under FEP-09/364/2009/C was on May 2014. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring stations are summarized
in Table 5.14 below.
Table 5.14
Air
Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.18
No exceedance was recorded in the reporting
month.
5.3.19
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
5.3.20
The commencement of construction works for
Contract no. HY/2010/08 under FEP-09/364/2009/B was on July 2014. Air quality
monitoring was commenced on 14 July 2011. The
proposed division of air quality monitoring stations are summarized in Table
5.15 below.
Table 5.15
Air
Quality Monitoring Station for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.21
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.3.22
Air quality monitoring for the Central
Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.16 below.
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
5.3.23
One 1hr TSP action limit level exceedance was
recorded on 27 August 2016 in the reporting month.
5.3.24
Only rebar fixing and formboard erection was
undertaken under Contract HK/2011/08 around the Oil Street Site Office during
the monitoring period and no particular observation regarding air quality
impact was observed during sample. In view of the above, the action level
exceedance was considered to be non-project related and contributed by local
ambient condition.
5.3.25
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
5.4.1.
Inert C&D wastes and non-inert C&D wastes were disposed in this
reporting month. Details of the waste flow table are summarized in
Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed, m3 |
57.86 |
107849.59 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
Nil |
98512.03 |
N/A |
Non-inert C&D materials disposed, m3 |
85.1 |
4903.76 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
Nil |
1284946 |
N/A |
Chemical waste disposed, kg |
Nil |
10400 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal) , m3 |
Nil |
11527 |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal) , m3 |
Nil |
16261 |
East of Cha Chau South Brothers |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.4.2.
Inert C&D & non-inert C&D wastes
were disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.18.
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
3 |
501570.412 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
Nil |
46520 |
N/A |
Non-inert C&D materials disposed, m3 |
238 |
3613.317 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
Nil |
N/A |
N/A |
Chemical waste disposed, kg |
Nil |
17718 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
Nil |
31086 |
South Cheung Chau |
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
5.4.3.
Inert C&D and non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
134.48 |
140683.94 |
||
Nil |
58787.05 |
||
21.98 |
4174.86 |
||
Nil |
878.37 |
||
Nil |
6772 |
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.4.
Inert & Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.20.
Table 5.20 Details of Waste Disposal for
Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
1944.4 Nil |
621670.77 245453.3 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled, m3 |
Nil |
358660.77 |
HY/2009/11 ex-PCWA TS4 /TS2 WDII Lun Ku Tan WENT HY/2010/08 |
Non-inert C&D
materials disposed, m3 |
78.29 |
4465.04 |
SENT Landfill |
Non-inert C&D
materials recycled, m3 |
Nil |
5496446.2 |
Xun Xiang Metalware
Skylight Recycle (paper) |
Chemical waste disposed, kg |
Nil |
22755 |
Dunwell Group |
Marine Sediment
(Type1-Open Sea Disposal (Dedicate Sites) &Type 2 – Confined Marine
Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
5.4.5.
Inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.21.
Table 5.21
Details of Waste Disposal for
Contract no. HY/2009/19
Inert
C&D materials disposed, ton |
6043.45 |
657494.74 |
N/A |
Inert
C&D materials recycled, ton |
Nil |
82349.7 |
N/A |
Non-inert
C&D materials disposed, ton |
79.14 |
5048.28 |
SENT Landfill |
Non-inert
C&D materials recycled, ton |
4.0 |
560.56 |
N/A |
Chemical
waste disposed, kg |
Nil |
9.92 |
N/A |
Marine
Sediment (Tunnel) (Type-1 Open Sea Disposal), m3 |
Nil |
20556 |
South of Cheung Chau |
Marine
Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 –
Confined Marine Disposal), m3 |
Nil |
30751 |
East of Sha Chau |
Contract no. HK/2012/08 Wan Chai
Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
5.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.22.
Table
5.22 Details of Waste Disposal for Contract
no. HK/2012/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
6394 |
172438 |
TKO 137 |
Inert
C&D materials recycled, m3 |
Nil |
84466 |
N/A |
Non-inert
C&D materials disposed, m3 |
280 |
2277 |
SENT |
Non-inert
C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical
waste disposed, kg |
Nil |
Nil |
N/A |
Marine
sediment (Type 1) disposal, m3 |
Nil |
3145 |
South of Cheung Chau / East of Sha Chau / South
of The Brothers |
Contract no. HY/2010/08
Central
– Wan Chai Bypass (CWB) – Tunnel (Slip Road 8) under FEP-10/364/2009/B
5.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.23.
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
9109.7 15884.4 Nil 131.4 |
567597.7 262656.6 82911.8 71198.7 |
TM 38 WENT SENT TKO area 137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
200.2 |
2301.06 |
SENT |
Non-inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical waste disposed, kg |
Nil |
979 |
N/A |
Type 1 – Open Sea Disposal, m3 |
Nil |
16368.4 |
East Sha Chau/ South Brothers Island |
Type 2 – Confined Marine disposal, m3 |
Nil |
549.2 |
East Sha Chau |
Table 5.23 Details of Waste Disposal for
Contract no. HY/2010/08
Contract no. HY/2011/08
Central
–Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning under FEP-11/364/2009B
5.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.24.
Table
5.24 Details of Waste Disposal for
Contract no. HY/2011/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
Nil |
367.68 |
CWPF & TKO137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
60.7 |
847.57 |
SENT |
Non-inert C&D materials recycled, ton |
Nil |
31.72 |
N/A |
Chemical waste disposed, kg |
Nil |
3800 |
N/A |
6.0.1.
The Event Action Plan for construction noise,
air qualities are presented in Appendix 6.1.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
6.1.1. No exceedance
was recorded in the reporting month.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Hong Kong Convention Exhibition Centre
– Tunnel Works under FEP-02/364/2009
6.1.2. No exceedance
was recorded in the reporting month.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.3. No exceedance
was recorded in the reporting month.
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
6.1.4. No exceedance
was recorded in the reporting month.
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.5. No exceedance
was recorded in the reporting month.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.1.6. No exceedance
was recorded in the reporting month.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
6.1.7. No exceedance
was recorded in the reporting month.
Real Time Noise Monitoring
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.8. Limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded on 09 August 2016 during daytime in the reporting month. After
checking with Contractor of HY/2009/19, no construction activities was
conducted during the recorded period while adverse weather with frequent thunderstorm
was observed and recorded across other monitoring stations at Tin Hau and North
Point District and is considered as the major noise contribution. As such, the
exceedance was considered not related to Project.
6.1.9. Limit level exceedances
were recorded at RTN2a-Electric Centre on 09 and 10 August 2016 during daytime in
the reporting month. After checking with Contractor of HY/2009/19, no
construction activity was conducted on 09 August 2016 during the recorded
period and unloading of soil at temporary jetty was conducted on 10 August 2016
during the recorded period. Adverse weather with frequent thunderstorm were
recorded at the monitoring period on 09 and 10 August 2016 across monitoring
stations at North Point District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related.
6.1.10. Limit level
exceedance was recorded at RTN3-Yue Lee Mo Fan Memorial School on 09, 10 and 17
August 2016 during daytime in the reporting month. After checking, no
construction works was conducted by Contract HY/2009/19 on 09, 10 and 17 August
2016 around the concerned location during the monitoring period while adverse
weather with frequent thunderstorm was recorded at the monitoring period on 09
and 10 August 2016 across monitoring stations at Eastern District and is
considered as the major noise contribution. As such, the exceedance was
considered as non-Project related.
On 17 August 2016, erection of U-beam with launching girder and crane
was conducted by HY/2009/19 on 17 August 2016 and no major noise is considered.
As such, the exceedance was considered as non-Project related.
6.1.11. Limit level
exceedances were recorded at RTN4-Causeway Bay Community Centre on 04, 09, 11,
12, 13 and 17 August 2016 during daytime in the reporting month. After checking
with the Contractor of HY/2009/19, excavation works and rebar fixing were
conducted by Contract HY/2009/19 on 04 August 2016 around the monitoring
location during the recorded period and no major noise is considered. In
addition, construction activities and intermittent operation of PMEs including
excavator, hydraulic breaker and sheet piling rig were observed at non-CWB
Project adjacent to monitoring station was observed in August 2016. As such,
the exceedances were considered as non-Project related.
On 09 August
2016, excavation and concreting works was conducted under Contract HY/2009/19
around the monitoring location during the recorded periods and no major noise
is considered for the works. In addition, construction activities and intermittent
operation of PMEs including excavator, hydraulic breaker and sheet piling
machine were observed at non-CWB Project adjacent to monitoring station over
August 2016. As such, the exceedances were considered as non-Project related.
On 11 August
2016 and 12 August 2016 morning, hand held drilling works at IEC bridge deck
(Pier 24) were conducted under HY/2009/19 and hand held breaking works beneath
IEC Bridge deck was conducted during the recorded period. No noise mitigation
measure was provided for the drilling works at IEC bridge deck on 12 August
2016 morning and was observed as the direct noise contribution. Hence, the
exceedances on 11 and 12 August 2016 were considered as related to the Project
works.
On 12 August
2016 afternoon, breaking works beneath the IEC bridge deck and concurrent
excavator mounted breaking works at Pier 23 were observed. Despite the
provision of temporary noise barrier for the ground breaking works by excavator
mounted hydraulic breaker and the hand held breaking works was observed
conducted behind physical barrier, exceedances were recorded and direct noise
contribution was observed in relation to the concurrent operation of hand held
breaker and excavator mounted hydraulic breakers opposite to the monitoring
station and considered as related to the Project works.
The ET informed
the findings to Contractor of HY/2009/19 and advised the Contractor of
HY/2009/19 to review the construction sequence to propose and implement
appropriate remedial actions. Rectification measure including provision of
acoustic noise screen for bridge deck drilling works was provided by the
Contractor of HY/2009/19 on 12 August 2016 and the Contractor of HY/2009/19
reviewed the construction sequence and committed to isolate concurrent bridge
deck drilling or hand held breaking for construction joint underneath IEC
bridge deck or excavator mounted breaking works to avoid cumulative impact due
to concurrent operations. Further checking by the ET was conducted on 14 August
2016, drilling works with acoustic noise screen was observed on IEC bridge deck
while no concurrent breaking works and drilling works was further observed on
14 August 2016 and no further project related exceedance was recorded.
On 13 August
2016, only excavation works was conducted by Contract HY/2009/19 around the
monitoring location during the recorded period and no major noise is
considered. In addition, construction activities and intermittent operation of
PMEs including excavator, hydraulic breaker and sheet piling rig were observed
at non-CWB Project adjacent to monitoring station was observed in August 2016.
As such, the exceedances were considered as non-Project related.
On 17 August
2016, drilling works for tie beam beneath IEC was conducted by Contract
HY/2009/19 immediately behind physical barrier erected around the works
location. In addition, construction activities and intermittent operation of
PMEs including excavator, hydraulic breaker and sheet piling rig were observed
at non-CWB Project adjacent to monitoring station was observed in August 2016.
As such, the exceedances were considered as non-Project related.
Contract no. HY/2011/08
Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
6.1.12. Limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded on 09 August 2016 during daytime in the reporting month. After
checking with Contractor of HY/2011/08, no construction activities was conducted
during the recorded period while adverse weather with frequent thunderstorm was
observed and recorded across other monitoring stations at Tin Hau and North
Point District and is considered as the major noise contribution. As such, the
exceedance was considered not related to Project.
6.1.13. Limit level exceedances
were recorded at RTN2a-Electric Centre on 09 and 10 August 2016 during daytime in
the reporting month. After checking with Contractor of HY/2009/19, no
construction activity was conducted on 09 August 2016 during the recorded
period and unloading of soil at temporary jetty was conducted on 10 August 2016
during the recorded period. Adverse weather with frequent thunderstorm were
recorded at the monitoring period on 09 and 10 August 2016 across monitoring
stations at North Point District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related.
6.1.14. Limit level
exceedances were recorded at RTN4-Causeway Bay Community Centre on 04, 09, 11,
12, 13 and 17 August 2016 during daytime in the reporting month. After checking
with the Contractor of HY/2011/08, no construction activities was conducted
around the monitoring location during the recorded period on 04, 09, 11, 12, 13
and 17 August 2016. In addition, construction activities and intermittent
operation of PMEs including excavator, hydraulic breaker and sheet piling rig
were observed at non-CWB Project adjacent to monitoring station was observed in
August 2016. As such, the exceedances were considered as non-Project related.
Contract no. HY/2009/18 – Central – Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
6.2.1.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre – Tunnel Works under FEP-02/364/2009
6.2.2.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.2.3.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
6.2.4.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.2.5.
One 1hr TSP action limit level exceedance was
recorded on 27 August 2016 in the reporting month.
6.2.6.
No construction activities was undertaken by
Contractor of HY/2009/19 around the Oil Street Site Office during the
monitoring period and no particular observation regarding air quality impact
was observed during sampling. Mitigation measures including watering for haul road
was generally implemented by the Contractor. In view of the above, the action
level exceedance was considered to be non-project related.
Contract no. HK/2012/08 Wan Chai Development Phase
II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
6.2.7.
No exceedance was recorded in the reporting
month.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.2.8.
No exceedance was recorded in the reporting
month.
Contract no. HY/2011/08
Central
–Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning under FEP-11/364/2009B
6.2.10.
Only rebar fixing and formboard erection was
undertaken under Contract HK/2011/08 around the Oil Street Site Office during
the monitoring period and no particular observation regarding air quality
impact was observed during sample. In view of the above, the action level
exceedance was considered to be non-project related and contributed by local
ambient condition.
6.3.1.
There was no non-compliance from the site
audits and monitoring in the reporting period. The observations and
recommendations made in each individual site audit session were presented in
Section 8.
6.4.1
There was no particular action taken since no
non-compliance was recorded from the site audits and monitoring in the
reporting period.
7.0.1.
According to Condition 3.4 of the
EP-364/2009/D, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Final
EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02,
the major construction activities were completed by end of January 2014 and no
construction activities were undertaken thereafter and the water
quality monitoring was completed in October 2011. As such, it is considered that there
were no cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting month.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area include structural works for tunnel construction, road works and drainage
works, and seawall modification were performed in August 2016 reporting month. As no project
related exceedance were recorded during the reporting period, cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was considered as insignificant.
7.0.4.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities under Wan Chai Development Phase II
were tunnel works at Wan Chai East and back filling works, culvert
reinstatement and road and drain works at Wan Chai West. The major construction
activities under Central-Wan Chai Bypass and Island Eastern Corridor Link
Projects were road works and ventilation building construction at Central
Interchange, temporary reclamation removal works at Ex-PCWAW, ELS works and
retaining wall construction at Victoria Park, ELS works and tunnel works at
TS3; bridge construction, piling and tunnel works at North Point area in the
reporting month. In addition, other non-Wan Chai Development Phase II,
Central-Wan Chai Bypass and Island Eastern Corridor Link projects was observed undertaken at Wan
Chai North and North Point area.
7.0.5.
No significant air quality impact from
construction activities was anticipated in the reporting month. Besides, no project
related exceedance was recorded during the air quality and noise environmental
monitoring events in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) was insignificant.
8.0.1.
During this reporting month, weekly
environmental site audits were conducted for Contracts no. HY/2009/15,
HY/2009/18, HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02, HY/2010/08 and HY/2011/08.
No non-conformance was identified during the site audits. The Contractors rectified major
observations and recommendations made during the audit sessions. No
non-conformance was identified during the site inspections.
8.0.2.
Site inspections for Contract no. HY/2009/15
were carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160809_1 |
9 Aug 2016 |
Impermeable
barrier shall be provided according to method statement to avoid potential
impact related to surface runoff at temporary cut slope (EX-PCWA) |
impermeable
barrier was provided |
Completion
as observed on 16 August 2016 |
160809_2 |
9 Aug 2016 |
Drip tray shall
be provided to chemical containers and leaked oil shall be cleared as
chemical waste (EX-PCWA) |
The
chemical waste was removed |
Completion
as observed on 23 August 2016 |
160816_1 |
16 Aug
2016 |
Damaged
impermeable barrier deployed around underwater excavation area shall be
repaired to avoid potential muddy dispersion and ensue the impermeable
barrier and silt curtain fully extended to seabed (EX-PCWA) |
The
condition of the impermeable barrier and silt curtain deployed was improved.
No further muddy seepage was observed |
Completion
as observed on 23 August 2016 |
8.0.3.
Site inspections for Contract no. HY/2009/18
were carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. HY/2009/18
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160818_1 |
18 Aug
2016 |
Protection
shall be provided to drainage system to avoid contaminated surface runoff and
cause contamination to nearby water |
Protection
was provided to drainage system |
Completion
as observed on 25 August 2016 |
160818_2 |
18 Aug
2016 |
Covering
shall be provide to stockpile and exposed surface to reduce the chance of
surface runoff and avoid dust emission during hot and dry weather. |
Covering
was provided to stockpile stored on-site |
Completion
as observed on 25 August 2016 |
8.0.4.
Site inspections for Contract no. HY/2009/19
were carried out during this reporting period. No observation was found in the
reporting month. The results of these inspections and outcomes are summarized
in Table 8.3.
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160727_1 |
27 Jul
2016 |
Proper chemical
container shall be provided to avoid leakage of chemical. The leaked chemical
waste (Pier35). |
Chemical
container was repaired to avoid leakage |
Completion
as observed on 3 August 2016 |
8.0.5.
Site inspections for Contract no. HK/2009/01
was carried out during this reporting period. No observation was found in
the reporting month.
8.0.6.
Site inspections for Contract no. HK/2009/02
were carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.5.
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160804_01 |
4 Aug 2016 |
Bunding
shall be provided at Portion 3&4 to prevent potential surface runoff into
nearby water body. |
Bunding
was provided at Portion 3&4. |
Completion
as observed on 11 August 2016 |
160804_02 |
4 Aug 2016 |
Floating
refuse shall be removed at Portion 5. |
Floating
refuse was cleared at Portion 5. |
Completion
as observed on 11 August 2016 |
160816_01 |
16 Aug
2016 |
NRMM label
shall be provided for generator in Portion 5. |
NRMM label
was provided for concerned generator in Portion 5. |
Completion
as observed on 25 August 2016 |
160825_01 |
25 Aug
2016 |
Hole of
drip tray shall be covered on-site for proper function. |
Hole of
drip tray is covered. |
Completion
as observed on 1 September 2016 |
8.0.7.
Site inspection for Contract no. HK/2012/08
were carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.6.
Table 8.6 Summary of Environmental Inspections for
Contract no. HK/2012/08
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
160727_01 |
27 Jul
2016 |
Removal of
silt & soft material at gate exit shall be implemented regularly to
prevent muddy trail on public road. |
Cleaning
at gate exit was properly implemented that no silt of soft material was
observed at gate exit. |
Completion
as observed on 3 August 2016 |
160803_01 |
3 Aug 2016 |
Muddy
dispersion was observed at the north of Zone B. The bunding along the
seafront shall be reinstated to avoid surface runoff into nearby water body
especially during heavy rainfall. |
Bunding
with geotextile covering was provided at the concerned location and no
potential surface runoff was observed. |
Completion
as observed on 16 August 2016 |
160816_01 |
16 Aug
2016 |
The hole
of drip tray under oil containers and generator shall be covered at Zone B |
The
hole of drip tray under oil and containers generator was covered. |
Completion
as observed on 23 August 2016 |
8.0.8.
Site inspections for Contract no. HY/2010/08
were carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.7
Table 8.7 Summary of
Environmental Inspections for Contract no. HY/2010/08
Item |
Date |
Observations |
Action
taken by Contractor |
Completion
date |
160727_1 |
27 Jul 2016 |
PME without NRMM Label shall not be operated
(TS3) |
NRMM label was provided for concerned PME |
Completion as observed on 3 August 2016 |
160803_1 |
3 Aug 2016 |
Drip tray shall be provided for chemical/oil
containers (Victoria Park) |
Drip tray was provided to oil container |
Completion as observed on 12 August 2016 |
160803_2 |
3 Aug 2016 |
Muddy seepage between seawall was observed. Silt curtain shall be provided along the
section of the seawall with seepage to avoid muddy diversion. (TS3 East) |
No more muddy seepage was observed |
Completion as observed on 12 August 2016 |
8.0.9.
Site inspections for Contract no. HY/2011/08
were carried out during this reporting period. No observation was found in the
reporting month.
9.0.1.
No environmental complaint, notification of summons and prosecution was
received in the reporting month.
9.0.2.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.3. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on
Complaints
Reporting Period |
No. of Complaints |
August 2016 |
0 |
September 2010 – July 2016 |
67 |
Total |
67 |
Table
9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be commenced in
Coming Reporting Month
Contract No. |
Key Construction
Works |
Recommended Mitigation Measures |
HY/2009/15 |
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE
and TPCWAW |
·
Dust control during dust generating activities and covering for
stockpile stored on site. ·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the nearby water. ·
Maintain regular cleaning of floating refuses within construction
area. |
HY/2009/18 |
·
Drainage works ·
Road works ·
Landscaping works ·
Modification and Construction of Sign Gantries / Traffic Signs ·
Maintenance works |
·
Dust control during dust generating activities ·
Provide protection works to ensure no runoff out of site area or
direct discharge into public drainage system. |
HY/2009/19 |
·
Approach ramp sheet piling, pre-bored piling and top soil removal
works ·
Bridge construction ·
Hing Fat Street modification works ·
Hing Fat Street Slip Road Bridge E L3 railing construction ·
EVB waterproofing & back filling works ·
Pier 22 to 28 Tie Beam construction continues ·
Oil Street drainage works ·
Excavation / Construction of retaining wall |
·
Noise level shall be controlled by reducing the breaking operation
rate. ·
Noise barrier shall be implemented ·
Dust control during dust generating works ·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. |
HK/2009/01 |
·
Reinstatement of outfall ·
Road and Drain works |
·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. ·
Dust control during dust generating works ·
Noise mitigation measures during breaking works |
HK/2009/02 |
·
Concreting of protective screeding on tunnel top slab ·
Tunnel wall and top slab construction ·
ELS S4 removal ·
Waterproofing layer at tunnel top slab ·
Tunnel backfilling ·
General cleaning of OHVD & tunnel base slap, carrier drain and
cross road duct. ·
Bulkhead wall removal works ·
Excavation work ·
Strut installation ·
Demolition of ex-WSD Salt Water Pumping Station |
·
Dust control during dust generating works ·
Proper maintenance boundary surface runoff protection and water treatment
facilities to avoid potential runoff related impact. ·
Provision of protection measures to ensure no runoff out of site area
or direct discharge into public drainage system. |
HK/2012/08 |
·
Grouting ·
Construction of MVB and CWB Tunnel ·
Construction of concrete plug ·
Excavation and lateral support installation for CWB tunnel |
·
Dust control during dust generating works ·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system. |
HY/2010/08 |
·
Tree protection works next to existing BGO, ·
Drainage improvement works, ·
Excavation and Lateral Support for U-structure, ·
Grouting works, ·
Utility diversion works, ·
Retaining wall works ·
ELS works, ·
Construction works for subway extension |
·
Dust control during dust generating works and stockpile stored on
site. ·
Appropriate measures should be taken to ensure adequate protections
are provided for trees being transplanted and retained on site. ·
Provision of protection to ensure no runoff out of site area or
direct discharge into public drainage system. |
HY/2011/08 |
·
Construction of Ventilation Buildings, inclusive of Administration
Building, East Ventilation Shaft/Building, West Ventilation Building ·
Construction of Tunnel Thermal Barrier ·
Installation of Electricals and Mechanicals ·
Installation of Tunnel Features |
·
Dust control during dust generating works |
10.0.3.
The construction works of Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
10.0.4.
The construction works of Contract no.
HY/2009/17 - Advance piling works at Whitfield Depot under FEP-03/264/2009 was
completed, and the FEP was surrendered by the Contractor and found in order by
EPD on 25 April 2013.
10.0.5.
The construction works of Contract HK/2010/06
was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3
October 2014.